SPTP — Section 7.1.2 Types of Analysis Methods, Dynamic Scheduling paragraph, page

  • Key: SPTP-100
  • Legacy Issue Number: 5067
  • Status: closed  
  • Source: U.S. Army Cecom-CSE ( Tom Wheeler)
  • Summary:

    This paragraph mentions “value based scheduling”. This phrase however, does not appear in following pages where tag – value pairs are defined for scheduling policies. Is the “MaxizeAccruedUtility” policy meant to cover value based scheduling? If so, I recommend the phrase “value based scheduling” be replaced with “utility-based scheduling”.

  • Reported: SPTP 1.0b1 — Wed, 20 Mar 2002 05:00 GMT
  • Disposition: Resolved — SPTP 1.0
  • Disposition Summary:

    Add reference to utility-based scheduling as alternative nomenclature

  • Updated: Fri, 6 Mar 2015 20:58 GMT