                            Key: UPDM2-38
 - 
                            Legacy Issue Number: 17617
 - 
                            Status: closed
 - 
                            Source: INCOSE ( Mr. Matthew Hause)
 - 
                            Summary:
DoDAF projects contain activities, similar to tasks on a MS Project diagram. Currently they do not have a time or sequence associated with them, making them problematic for defining a chronological order or sequence. Consequently I cannot see how the can define a project sequence of tasks. For the MODAF AcV-2 we use the date field of the actual project milestone. MS Project tasks can contain sequence dependencies as well as specific start times and durations. The activities will require either a chronological before/after or the creation of an activity diagram for support.
 - 
                            Reported: UPDM 2.0 — Fri, 21 Sep 2012 04:00 GMT
 - 
                            Disposition: Resolved — UPDM 2.0.1
 - 
                            Disposition Summary:
see pages 68 through 70 of dtc/2012-12-16 for details
 - 
                            Updated: Fri, 6 Mar 2015 20:59 GMT
 
UPDM2 — Missing sequencing capability for DoDAF Project Activities
- Key: UPDM2-38
 - OMG Task Force: UPDM 2.0 FTF