UPDM 2.0 FTF Avatar
  1. OMG Issue

UPDM2 — Missing sequencing capability for DoDAF Project Activities

  • Key: UPDM2-38
  • Legacy Issue Number: 17617
  • Status: closed  
  • Source: INCOSE ( Mr. Matthew Hause)
  • Summary:

    DoDAF projects contain activities, similar to tasks on a MS Project diagram. Currently they do not have a time or sequence associated with them, making them problematic for defining a chronological order or sequence. Consequently I cannot see how the can define a project sequence of tasks. For the MODAF AcV-2 we use the date field of the actual project milestone. MS Project tasks can contain sequence dependencies as well as specific start times and durations. The activities will require either a chronological before/after or the creation of an activity diagram for support.

  • Reported: UPDM 2.0 — Fri, 21 Sep 2012 04:00 GMT
  • Disposition: Resolved — UPDM 2.0.1
  • Disposition Summary:

    see pages 68 through 70 of dtc/2012-12-16 for details

  • Updated: Fri, 6 Mar 2015 20:59 GMT