Key: UML25-281
-
Legacy Issue Number: 17841
-
Status: closed
-
Source: Change Vision ( Michael Chonoles)
-
Summary:
The notation in Figure 17.5 for timing annotation on sequence diagram does not match the almost identical diagram of Figure 8.5
-
Reported: UML 2.4.1 — Wed, 26 Sep 2012 04:00 GMT
-
Disposition: Resolved — UML 2.5
-
Disposition Summary:
Figure 8.5 should match Figure 17.5. Figure 17.5 is the more correct of the two. However, Figure 17.5
highlights the terms ’duration’ and ’now’ in bold style. This may people mislead to the assumption that
these terms are kind of predefined keywords, which is not the case. So that could be improved, two.
This also resolves Issue 10974. -
Updated: Fri, 6 Mar 2015 20:59 GMT