Key: BPMN2-98
-
Legacy Issue Number: 14564
-
Status: closed
-
Source: Dresden University of Technology ( Frank Toeppel)
-
Summary:
maybe I’m wrong, but it seems there’s a logic error in the PDF document mentioned above:
- Figure 12.36 shows a Choreography starting with communication from A (initiator) to B. Depending on message content based decision next message will be sent from A to B (decision YES) or from A to C (decision NO).
- Comparing that to the corresponding Collaboration in Figure 12.37 I detected a mismatch, within Pool A the gateway acts inverse: If decision YES message M3 will be sent from A to C, and if decision NO message will be sent from A to B
- Looks like content of pool A should be adapted (decision YES should result in message from A to B)
Furthermore there seems to be an offset to Figure indices listed in some chapters vs. the real Figure numbers:
- Check chapter 10.2.8 (Loop Characteristics in Process Diagrams)
- Scroll to page 169 (PDF document page 199), chapter Standard Loop Characteristics
- You will find a link to Figure 10.42 and 10.43 (see Figure 10.42 and Figure 10.43)
- Corresponding figures instead are 10.43 and 10.44
- This offset stuff starts somewhere before in the document, maybe an additional picture has been added
-
Reported: BPMN 2.0b1 — Thu, 15 Oct 2009 04:00 GMT
-
Disposition: Resolved — BPMN 2.0
-
Disposition Summary:
(a) Replace Figure 12.36 with a figure that has the positioning of the Participants in the Participant Bands more consistent. See here:
(Replacement+for+Figure+12.36.jpg)
(b) Replace Figure 12.37 with a figure that sequence of activities are matching those of Figure 12.36. See here:
(10571_Replacement+for+Figure+12.37.jpg)
(c) Section 10.2.8 Loop Characteristics, Sub-Section Standard Loop Characteristics, page 169 (199 pdf), first bullet in section: replace "Figure 10.42" with "Figure
10.43" and replace "Figure 10.43" with "Figure 10.44."
Disposition: Resolved -
Updated: Fri, 6 Mar 2015 20:57 GMT