Key: BPMN2-116
-
Legacy Issue Number: 14652
-
Status: closed
-
Source: NIST ( Mr. Conrad Bock)
-
Summary:
The private process in Figure 10-122 (One Process supporting to another)
should have activity X and event B in parallel, because event B may
arrive while X is executing, which would be lost in the current example.
See webinar example on slide 51 in bmi/09-06-02. -
Reported: BPMN 2.0b1 — Thu, 19 Nov 2009 05:00 GMT
-
Disposition: Resolved — BPMN 2.0
-
Disposition Summary:
(a) Replace Figure 10.123 (One Process supporting to another) with the one given in the attachment
BPMNFTF-341-private-process-example.pdf.
(b) In paragraph above Figure 10.123, next to last sentence (the one beginning "It also introduces"), replace "Activity" with "Activities".
Disposition: Resolved -
Updated: Fri, 6 Mar 2015 20:57 GMT