BPMN 1.1 NO IDEA Avatar
  1. OMG Issue

BPMN11 — Clarify whether pools require their activites to be centrally coordinated

  • Key: BPMN11-62
  • Legacy Issue Number: 10340
  • Status: closed  
  • Source: NIST ( Mr. Conrad Bock)
  • Summary:

    Clarify whether pools require their activites to be centrally coordinated. In particular, above Table 85, the specification says: "Note that Message Flow cannot connect to objects that are within the same Participant Lane boundary." (I think this should say "pool", rather than "lane".) Does this mean the entities represented by lanes must not coordinate their activities directly through messages to each other (ie, the coordination must be centralized)?

  • Reported: BPMN 1.0b1 — Tue, 5 Sep 2006 04:00 GMT
  • Disposition: Resolved — BPMN 1.1
  • Disposition Summary:

    see above

  • Updated: Fri, 6 Mar 2015 20:57 GMT