BPMN 1.1 NO IDEA Avatar
  1. OMG Issue

BPMN11 — MessageFlows to a subprocess boundary

  • Key: BPMN11-46
  • Legacy Issue Number: 9903
  • Status: closed  
  • Source: International Business Machines ( Ms. Suzette Samoojh)
  • Summary:

    Page 103 states that
    If the Message Flow is connected to the boundary of the Expanded
    Sub-Process, then this is equivalent to connecting to the Start Event
    for incoming Message Flow or the End Event for outgoing Message Flow
    (see Figure 10.7).

    Does this make sense, considering that the Sub-Process may contain
    Send/Receive Tasks and Message Intermediate Events? If we remove this
    sentence, then we should also remove Figure 10.7.

  • Reported: BPMN 1.0b1 — Thu, 6 Jul 2006 04:00 GMT
  • Disposition: Resolved — BPMN 1.1
  • Disposition Summary:

    see above

  • Updated: Fri, 6 Mar 2015 20:57 GMT