-
Key: UTP12-16
-
Legacy Issue Number: 15914
-
Status: open
-
Source: sepp.med ( Armin Metzger)
-
Summary:
Some test cases might required additional hardware that is only available in specific timeframes. This means the test cases must be scheduled in detail and in certain sequences. Also, test cases may depend on each other.
Corresponding model element assignments can be established in principle with the current UTP specification, but a corresponding rule-set or a basic standard is missing.
Such kind of rule-set standard is necessary for potential tooling support of scheduling aspects coming out of an UTP test model.
-
Reported: UTP 1.0 — Wed, 5 Jan 2011 05:00 GMT
-
Updated: Fri, 6 Mar 2015 20:59 GMT
UTP12 — Test scheduling should be supported explecitely
- Key: UTP12-16
- OMG Task Force: UML Testing Profile 1.2 (UTP) RTF