                            Key: UPDM2-5
 - 
                            Legacy Issue Number: 16578
 - 
                            Status: closed
 - 
                            Source: Dassault Systemes ( Dr. Aurelijus Morkevicius)
 - 
                            Summary:
I would suggest Project Sequence would have a tag Sequence Kind to store values like "start-to-start", "start-to-finish", "finish-to-start", and “finish-to-finish".
 - 
                            Reported: UPDM 1.1 — Mon, 3 Oct 2011 04:00 GMT
 - 
                            Disposition: Resolved — UPDM 2.0.1
 - 
                            Disposition Summary:
The rationale behind the request is that it keeps alignment with standard project management tools. Aurelijus suggested a text field to describe this relationships, Lars said this is outside the intent of MODAF and there is an implicit understanding that a target project cannot start until source project finishes.
There is a workaround which is to use measurements applied to project to capture this information.
Therefore it was decided to close this issue with no change
Proposed Disposition: Closed, no change
 - 
                            Updated: Fri, 6 Mar 2015 20:59 GMT