Key: SPEM11-5
-
Legacy Issue Number: 5331
-
Status: closed
-
Source: Softeam ( Philippe Desfray)
-
Summary:
The SPEM standard says :
"A Trace dependency acts between WorkDefinitions and is mainly
used to trace requirements and changes across models. It has the same
semantics as UML Trace."Trace should not apply only on WorkDefinition but on every model element. We
could have for examples a requirement on process, and trace a specific
activity to the requirement, thus expressing that we have defined this
activity to fulfill the requirement. This is in line with the UML semantics. -
Reported: SPEM 1.0 — Wed, 29 May 2002 04:00 GMT
-
Disposition: Resolved — SPEM 1.1
-
Disposition Summary:
This is a change to the specification text, with no change to the metamodel.
-
Updated: Fri, 6 Mar 2015 20:58 GMT
SPEM11 — Trace should not apply only on WorkDefinition but on every model element
- Key: SPEM11-5
- OMG Task Force: SPEM 2003 RTF