Key: BPMN11-85
-
Legacy Issue Number: 10527
-
Status: closed
-
Source: BPM Advantage Consulting ( Dr. Stephen White)
-
Summary:
Project management models define the start/finish relationships between activities. This is handled in four ways: Finish-Finish; Finish-Start; Start-Finish; and Start-Start. Current BPMN Flow handles two of the four. A sequential flow of activities is a Finish-Start; a parallel set of activities is a Start-Start. But the other two combinations are not definable. The solution may not require graphical canges to BPMN, but there should be some behavioral support for these situations.
-
Reported: BPMN 1.0 — Fri, 15 Dec 2006 05:00 GMT
-
Disposition: Resolved — BPMN 1.1
-
Disposition Summary:
Suggested Resolution:
Close, No Change: This issue is out of scope for the RTF and will be addressed by the response to
the BPMN 2.0 RFP.
Revised Text: None
Disposition: Closed, deferred -
Updated: Fri, 6 Mar 2015 20:57 GMT